Eaton Fire rebuild · Pasadena
Pasadena Fire Rebuild Contractor, From City Permit to Move-In
Rebuilding in Pasadena after the Eaton Fire: who permits your lot, what the City asks for, and what it took to take our Woodlyn Road rebuild from a cleared lot to final details.
Architectural DigestAD PRO · Featured 2026
If your home in Pasadena burned in the Eaton Fire, the first thing to know is that rebuilding here isn’t the same as rebuilding in Altadena. Inside the city limits, your plans go through the City of Pasadena, its own departments, and its own utility, Pasadena Water and Power. As a Pasadena fire rebuild contractor that has taken a home through that process, we can show you what it actually involves.
Our office is at 2235 Lake Ave in Altadena, a short drive from the Pasadena neighborhoods the fire reached. We’ve advised 109 fire-affected households since January 2025 and currently have 13 active rebuilds across Pasadena, Altadena, and Pacific Palisades. Read at your own pace, or call us at (844) 464-6460 and we’ll tell you which office holds your permit.
Every lot is different, and nothing here replaces a conversation with your insurer, your engineer, or us. For our other areas, see all our fire rebuild resources.
Start where you are
Where are you right now?
Proof, with an address
Our Woodlyn Road Rebuild in Pasadena
Liwen’s home on Woodlyn Road burned in the Eaton Fire. Here’s how the rebuild went, with the dates from the City’s own approvals.
The design goal was a warm, contemporary home built around simplicity and comfort: natural materials, subtle textures, and warm lighting. The old foundation couldn’t be reused, so the house sits on a completely new slab.
From cleared lot to roof, from the air




The permit, date by date
- May 20, 2025Plans submitted to the City of Pasadena.
- June 5, 2025First corrections back, 16 days later.
- July 2, 2025Second round of corrections.
- September 2025City department sign-offs come in, one by one.
- October 8, 2025Final City sign-off on the approved set.
- December 3, 2025Construction starts.
- NowFinal finishing details.
The hardest part was the utility, not the house. Pasadena runs its own utility, Pasadena Water and Power. Resolving the underground electrical service with them took about three months, and getting final power has been the slowest part of the job. Everything else (the subs, the construction, the selections) ran smoothly. If you’re rebuilding in the city, start the conversation with Water and Power early.
City inspectors in Pasadena have high expectations, and changes take time to get approved. The last finishing details have taken the longest. The rest of the build has been straightforward.
GO Home Builders reviews
What Homeowners Say About Working With Us
Fire rebuild
Different right away
“We talked to a few builders after the fire, but Go Home Builders felt different right away. Oren was easy to talk to, honest about the process, and made us feel heard. Rebuilding in Altadena is not easy, but having the right team beside you makes all the difference.”
Fire rebuild
Insurance money secured
“Working with the insurance was a pain, luckily Gil had experience working with Allstate insurance before, and he helped us a lot getting the money we needed to rebuild our home.”
Custom home
The best decision we made
“They took the time to understand how we live, what matters to us, and how we wanted our home to feel. The design they created was perfect and the construction quality matched. We always felt heard, we always felt respected.”
Ask to talk to a past client with a build like yours, or walk an active site.
Step 1 · Who permits your lot
City of Pasadena or Los Angeles County?
A Pasadena mailing address doesn’t decide who permits your rebuild. Lots inside the city limits go through the City of Pasadena. Unincorporated areas, including Altadena and some lots with Pasadena addresses, go through Los Angeles County. Find out which before anyone draws a line, because the departments, the rules, and the timeline are different.
Inside the city: City of Pasadena
Plans are reviewed by the City’s building division and plan check, with Planning, Fire, Public Works, Transportation, and Pasadena Water and Power each signing off. Woodlyn Road went this way.
Unincorporated: Los Angeles County
Plans are filed through EPIC-LA and reviewed by County departments. In our experience, County corrections take about four weeks. Here’s how we handle Altadena fire rebuilds, and how County and City rebuilds compare.
How much bigger can you rebuild?
On Woodlyn, the City checked the new home against the original plus 10%. The old house and garage totaled 1,933 sq ft, which capped the rebuild at about 2,126 sq ft. The new home and garage come to 2,001 sq ft, inside the limit. If you want to go bigger than that, expect more review and confirm the path for your lot before you design.
Step 2 · Plan check
What the City of Pasadena Asked For on Our Rebuild
These came straight from the City’s corrections and approvals on Woodlyn Road. Plan for them from the first sketch and you stay at two rounds of corrections, which is the standard we hold every project to.
The City required a soils report for the fire rebuild before approving the foundation.
A landscape plan by a California-registered landscape architect, and possibly a water-efficient landscape (MWELO) report.
The City required a solar (PV) system installed before the final inspection, even on a fire rebuild. In our experience, Altadena and Pacific Palisades rebuilds haven’t had this requirement. Budget for it in Pasadena.
NFPA 13D residential sprinklers, plus Pasadena Water and Power’s backflow device rules for the water service.
Upgrading the main panel meant booking an on-site meter appointment with Pasadena Water and Power before they’d approve it. Only one main panel is allowed per parcel.
Any damaged curb, gutter, or sidewalk out front has to be repaired under a separate Public Works permit before the certificate of occupancy. Loading and parking for the job have to stay on site.
Not every burned lot in Pasadena sits in a mapped fire hazard severity zone, and the zone affects which wildfire construction rules apply. Woodlyn’s plans list it outside one. Check your parcel early. For lots that are in one, here’s what the California wildfire code requires.
Already have plans?
Plans in Hand, Need a Builder
If your architect already has a set in plan check or approved, we’ll build it. We review the plans for cost and buildability before you commit, price them line by line, take over as contractor of record, and build.
Starting from scratch instead?
Design, engineering, permits, and construction come from one team under one contract, and you get a fixed price before the plans are final. Here’s how we build, from sketch to keys. Building new in Pasadena rather than rebuilding? See our custom home builder page for Pasadena.
Send us your plansStep 3 · The claim
Turning Your Insurance Claim Into a Real Budget
Insurance is meant to put back what you lost. A Pasadena rebuild has to meet today’s code, which on Woodlyn meant a soils report, sprinklers, solar, and a licensed landscape plan. Those costs belong in the right part of your claim.
What we do on the claim
We write the scope in Xactimate, the estimating software insurance carriers use, with code-required upgrades listed separately so they can be claimed under code-upgrade coverage. If a carrier pushes back on scope, we push back too.
We’re builders, not insurance professionals. For questions about what your policy covers, talk to your insurer, a licensed public adjuster, or an attorney.
Start with a real number
Watch the pricing video above for what Woodlyn cost, or try our build-a-home cost calculator for a starting figure on your lot. You get a fixed price from us before your plans are final.
Choosing a builder
Choosing the Right Pasadena Fire Rebuild Contractor
The cheapest bid is usually the least detailed one. Here’s what you get with us, and what to ask any builder for.
People you can reach in month fourteen
Every project has a dedicated project manager and a dedicated designer, and a Buildertrend client portal from day one with your schedule, budget, selections, change orders, photos, and a daily log from the site. We cap ourselves at 15 active projects.
We submit our own plans
No permit expediter. Corrections come straight back to the people who drew the house, and we hold every project to two rounds.
Proof before you sign
Walk an active job site, call past clients, and check the license on the CSLB website. Here’s how to vet a fire rebuild contractor.


Who issues fire rebuild permits in Pasadena?
It depends on where the lot sits. Inside the city limits, the City of Pasadena issues the permit, with Planning, Fire, Public Works, Transportation, and Pasadena Water and Power each reviewing the plans. Unincorporated areas, including Altadena and some lots with Pasadena mailing addresses, are permitted by Los Angeles County.
How long does a Pasadena fire rebuild permit take?
On our Woodlyn Road rebuild, we submitted plans on May 20, 2025, got first corrections 16 days later, a second round on July 2, and final City sign-off on October 8, 2025. That’s about four to four and a half months from submittal to an approved set, with two rounds of corrections.
Does Pasadena require solar on a fire rebuild?
On our Woodlyn Road rebuild, yes. The City of Pasadena required a solar system installed before the final inspection. In our experience, Altadena and Pacific Palisades rebuilds haven’t had that requirement. Confirm it for your lot and include it in your budget.
How much bigger can I rebuild in Pasadena?
On Woodlyn Road, the City checked the new home against the original floor area plus 10%. The original house and garage were 1,933 sq ft, which capped the rebuild at about 2,126 sq ft, and the new home and garage total 2,001 sq ft. Going larger can mean more review, so confirm your path before you design.
Do you build from plans another architect drew?
Yes. We review the plans for cost and buildability, price them line by line, take over as contractor of record, and build.
What took the longest on your Pasadena rebuild?
Coordinating with Pasadena Water and Power. Resolving the underground electrical service took about three months, and getting final power has been the slowest part of the job. Start that conversation early if you’re rebuilding inside the city.
Rebuilding in Pasadena? Start With Your Lot.
Tell us your address and where you are in the process. We’ll tell you whether the City or the County holds your permit, what they’re likely to ask for, and what comes next. The first conversation is free.