Will Your Living-Expense Coverage Run Out Before Your House Is Done? What Happens at the Two-Year Mark
Last updated: October, 2026
For homeowners rebuilding after the Eaton and Palisades fires, January 7, 2027, is an important milestone for additional living expense (ALE) coverage. But it is not an automatic cutoff for every claim. Under California Insurance Code Section 2060, homeowners may qualify for extensions when reconstruction delays are beyond their control. Policy dollar limits still apply, and the documentation behind an extension request matters.
At Go Home Builders, we see how permitting, construction scheduling, and contractor problems can affect a rebuild. Here is what homeowners should know about the two-year mark and how their builder can help document the project’s progress.
What This Looks Like on a Real Rebuild
One of our clients in Pacific Palisades is approaching the two-year mark. Her rebuild did not fall behind because of her, but because she hired a builder who started the plans and then stopped working on them. More than a year passed. When things started to feel wrong, she checked the contractor’s license on the Contractors State License Board (CSLB) website and discovered that it had been revoked.
She terminated that relationship and hired Go Home Builders. We restarted the plans, which are now with the City of Los Angeles awaiting approval.
She is now requesting an additional year of ALE coverage from her insurer. To support the request, the insurer asked for our contract, an explanation of the delay, dates for plan submissions and other project milestones, and relevant City documents. In some cases, insurers also ask for job site photographs. The goal is to understand what caused the delay and whether the project is now moving forward.
Her extension request is still in progress. We cannot say whether it will be approved, but we can provide the construction records that help explain the timeline.
This is exactly why we tell homeowners to check a contractor’s license before they sign.
Does ALE End on January 7, 2027?
No. January 7, 2027, marks 24 months from the start of the Eaton and Palisades fires for many affected homeowners, but it does not automatically end every ALE claim.
California Insurance Code Section 2060 provides that ALE coverage for a covered loss related to a declared state of emergency must last at least 24 months from the inception of the loss, subject to other policy provisions. The statute also provides for an extension of up to 12 additional months when the homeowner acts in good faith and with reasonable diligence and encounters qualifying reconstruction delays beyond their control.
Additional six-month extensions must be provided for good cause. The amount available under the policy remains a separate consideration.
For homeowners still in permitting or construction, the important next step is to understand the applicable policy provisions, remaining benefit amount, and documentation needed to support an extension request.
Can I Get More Than 24 Months of ALE Coverage?
California law provides for up to 12 additional months, bringing the total to 36 months, when the statutory requirements are met. Section 2060 identifies examples of circumstances beyond the homeowner’s control, including unavoidable construction permit delays, lack of necessary construction materials, and lack of available contractors.
The law also provides for additional six-month extensions for good cause. Whether an individual homeowner qualifies depends on the circumstances and applicable policy provisions.
The key is to establish what happened and when. A project that remains in plan review has a different timeline from one that has been permitted but is waiting for materials or inspections. A clear record helps explain the actual circumstances rather than simply showing that the house is unfinished.
What Documentation Helps an ALE Extension Request?
The most useful documentation starts with the records the insurer actually requested in our Pacific Palisades client’s case. Homeowners can ask their builder to help assemble the following.
- The construction contract. This establishes the working relationship, scope of work, and relevant project details.
- An explanation of the delay. A dated project timeline should explain what happened, when the problem arose, and how it affected progress. In our client’s case, the previous builder’s failure to continue the plans was a key part of the timeline.
- Dated project milestones. These can include plan submission dates, correction letters, resubmission dates, project start dates, permit issuance, and other significant milestones.
- City or County documents. Copies of plan-check comments, correction notices, permit records, and other relevant agency communications can help establish the permitting history.
- Job site photographs. Insurers may request photographs to document the property’s condition and construction progress. Keep dated images when available.
Beyond those items, additional records may help explain delays when they are relevant to the project:
- Current construction schedule: A realistic completion estimate showing completed work, outstanding tasks, and remaining dependencies.
- Inspection records: Inspection dates, results, rescheduled appointments, required corrections, and the reasons for delays where known.
- Material delivery records: When material shortages or delivery delays affect the schedule, we can gather relevant supplier communications, order information, and revised delivery dates.
- Daily logs: We use Buildertrend to maintain dated records of site activity and project progress, helping establish what happened during construction.
These documents do not guarantee an extension. Their purpose is to provide an accurate, organized record of the project’s history and the reasons for delay.
The homeowner, public adjuster, or attorney makes the extension request to the insurer. Our role as the builder is to provide relevant construction documentation when requested.
How We Save Time When ALE Is Running Out
When a client’s living expenses are close to running out, two things save us the most time.
First, we start demolition and grading before the building plans are approved, where the required permits allow it. In our experience, this saves three to four weeks, so the site is ready when the building permit is issued. The specific work that can begin depends on the permits and approvals required for that property.
Second, we finish the design and finish selections while the plans are in plan check. Once the homeowner approves the selections, we can order finish materials early so construction does not stop and wait for deliveries.
These steps help us prepare for the next phase rather than waiting until one stage is complete to begin planning the next. They do not eliminate every delay, but they can reduce avoidable downtime.
We also keep track of project milestones and schedule changes so homeowners can understand where their rebuild stands. Our Fair Oaks rebuild in Altadena took about four months from the first sketch to permit issuance, followed by about ten months of construction. That is approximately 14 months from the first sketch through construction on that particular project.
A home that breaks ground after about March 2026 and follows that same ten-month construction schedule would finish after the 24-month mark. That does not mean coverage ends; it means the extension request matters.
This is an illustration, not a prediction for every property. Actual timelines vary with the permitting process, design requirements, construction scope, material availability, and other project-specific circumstances.
For more detail, read our guide to how long it takes to get a rebuild permit in Altadena and our Fair Oaks Altadena rebuild example.
What If My ALE Dollar Limit Runs Out First?
An extension of time does not automatically increase the amount of money available under a policy. A homeowner’s ALE dollar limit may be exhausted before the applicable coverage period ends.
Ask your insurer for your ALE payment history, remaining benefit amount, and a written explanation of the time limits and dollar limits that apply to your claim. Reviewing these figures before the two-year milestone can help you understand the questions you need to resolve.
For coverage questions, talk to your insurer, a licensed public adjuster, or an attorney. You can also contact the California Department of Insurance Consumer Hotline at 1-800-927-4357.
Is the Replacement-Cost Deadline the Same as the ALE Deadline?
No. ALE coverage and the deadline to collect full replacement cost are separate timelines.
Under California Insurance Code Section 2051.5(b)(1)(B), for a loss relating to a declared state of emergency, an insurer cannot impose a time limit of less than 36 months from the date of the first payment toward actual cash value for collecting full replacement cost, subject to the policy limit.
Section 2051.5(b)(2) further states that an insurer shall provide one or more additional six-month extensions for good cause when the insured, acting in good faith and with reasonable diligence, encounters delays in approval for or reconstruction of the home that are beyond the insured’s control. The statute identifies unavoidable construction permit delays, lack of necessary construction materials, and unavailable contractors as examples.
This is a separate clock from ALE. The replacement-cost period is measured from the first actual cash value payment, not simply the date of the fire.
Homeowners should confirm the relevant payment date and applicable deadlines with their insurance representative. For more on how rebuilding requirements can affect costs beyond the original home’s replacement, see our guide to insurance coverage and rebuild requirements.
Sources:
California Insurance Code Section 2051.5
California Department of Insurance’s 2026 guide for adjusting property claims after a major disaster
What Should I Do Before January 2027?
If your rebuild is still in permitting or construction, take these steps before the 24-month milestone:
- Ask your insurer for your ALE payment history and remaining limit. Confirm how much has been paid and what remains available.
- Request your construction records. Ask your builder for the contract, project timeline, permitting documents, relevant photographs, and records of delays.
- Put your extension request in writing before the 24-month mark. Discuss the timing and supporting documents with your insurer or qualified insurance representative.
- Confirm your remaining construction schedule. Ask what work remains and what could affect the projected completion date.
- Get advice on your coverage. Talk to your insurer, a licensed public adjuster, or an attorney about your policy and individual circumstances. The California Department of Insurance Consumer Hotline is 1-800-927-4357.
The two-year mark is a reason to review your timeline and organize your records, not to assume that coverage automatically ends on January 7.
Frequently Asked Questions
No. January 7, 2027, is the 24-month milestone for many Eaton and Palisades fire claims, but it is not an automatic cutoff for every claim. California Insurance Code Section 2060 provides for extensions when statutory requirements are met, subject to other policy provisions and applicable dollar limits.
California Insurance Code Section 2060 provides for an extension of up to 12 additional months, for a total of 36 months, when the homeowner acts in good faith and with reasonable diligence and encounters qualifying reconstruction delays beyond their control. Additional six-month extensions must be provided for good cause. Individual coverage questions should be reviewed with the insurer or a qualified insurance professional.
The statute identifies unavoidable construction permit delays, lack of necessary construction materials, and lack of available contractors as examples of circumstances beyond the homeowner's control. Whether a particular delay supports an extension depends on the circumstances and applicable policy provisions.
Useful records may include permit submission and correction dates, resubmission records, a current construction schedule, material lead times and delivery updates, inspection records, daily construction logs, and dated photographs. These records can help explain the timeline, but they do not guarantee approval of an extension.
A policy's ALE dollar limit may be exhausted before the applicable coverage period ends. An extension of time does not automatically increase the available dollar limit. Ask your insurer for your payment history, remaining benefit amount, and an explanation of the provisions that apply to your claim.
In our experience, our Fair Oaks rebuild took about four months from the first sketch to permit issuance and about ten months of construction, or approximately 14 months in total. In Altadena, the period from a cleared lot to permit issuance can be about four to seven months. Actual timelines vary by property, permitting process, construction scope, and other project-specific factors.
No. ALE coverage and the deadline to collect full replacement cost are separate. Under California Insurance Code Section 2051.5, a loss related to a declared state of emergency has a minimum 36-month period to collect full replacement cost, measured from the first actual cash value payment and subject to the policy limit. Additional six-month extensions are provided for good cause when statutory conditions are met.
Ask your insurer for your ALE payment history and remaining dollar limit, request a dated project timeline and supporting records from your builder, put your extension request in writing before the 24-month milestone, and seek guidance from your insurer, a licensed public adjuster, or an attorney about your specific coverage questions. You can contact the California Department of Insurance at 1-800-927-4357.